I’ll come down to the space this week - probably wednesday - and do an appraisal of our current piles and what’s needed to build this wall. In general, I’m planning on independent inner and outer frames of 50x75 studs, with staggered verticals, for best sound isolation. We’ll only build one layer for now.
Do we have any timber left that fits this spec or should I assume all new?
Also, how much of the birch ply is there left?
For doors, someone needs to drive to the reclaim yard here:
And see what they’ve got. Unfortunately, their phone number was in my old phone which is very dead. We only really need 1 solid for the block wall, and a pair with vision panels for the short wall. The dimensions of those doors will inform everything else.
sigh my work life has become a bit complicated again. As a result I can’t host make the space for the next couple Sundays. It would be really important for someone else to take charge of fore manning these two weeks.
To slightly make up for it, I’m happy to lead a team from early evening into the wee hours of Saturday night if there are volunteers?
Just a reminder: we have the IoT workshop running from 10 to 5 on Saturday, so space makers will need to be sensitive to that. However, from my memory of putting up lining that probably just means slightly quieter cursing…
well done on the doors Dermot…not getting them would have potentially slowed the great momentum we have going.
We should be able to start the first stud wall very soon, if i’m right we have an agreed drawing from TomN for this