Lots of disruption in arch 2 (arch 1 should be business as usual) - any volunteer help would be very appreciated, we’ll need to drag lots of stuff out of the snug to make way for the new spray booth
If you want to learn how to pour concrete or just feel smug when the new metal shop / ceramics area opens, now’s a good opportunity!
Plan is: Saturday morning, drag loads of stuff out of the snug / back of arch 2, pour concrete for the spray booth, a new step that’s needed, concrete plinth for machines AND minor repairs / levelling elsewhere
Wood shop will likely have lots of stuff temporarily dumped in it (with permission from 2 wood techs), but there may be some usable space in there if someone wants to use it
This unfortunately is no longer happening - with workers that are now coming in on Thursday there’s no feasible way for me to do the prep work needed or to calculate quantities for this to go ahead
Another slight update on this - I’d overestimated what “removing the asbestos” would entail, looks like everything has pretty much been left in place, so I’ve booked in the Selco order for saturday and will most likely be doing rebar on saturday and concrete sunday afternoon.
For this weekend we’re just doing the concrete plinth, then as things move into their permanent homes and we gain a bit of wiggle room we can start tackling other areas.
There’s a mixer being delivered saturday morning and collected monday afternoon by the way, so if we have any miscellaneous concreting jobs to do then now’s the time